Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Renewable energy » KPI Green Energy Commissions First Phase of 250 MW GUVNL Solar Project Ahead of Schedule
Renewable energy

KPI Green Energy Commissions First Phase of 250 MW GUVNL Solar Project Ahead of Schedule

ManshiBy ManshiJanuary 23, 20262 Mins Read
Facebook Twitter LinkedIn WhatsApp
KPI Green Energy Commissions First Phase of 250 MW GUVNL Solar Project Ahead of Schedule

Renewable energy developer and builder KPI Green Energy has achieved an early major milestone in the implementation of its large grid connected solar power project contract with Gujarat Urja Vikas Nigam Limited (GUVNL). The company announced the early commissioning of the first phase of its 250 MW AC/350 MW DC solar Independent Power Producer (IPP) project.

In an official statement, the kWh solar power plant capacity has been confirmed to stand at an initial capacity of 24.2 MW AC/34.4 MW DC, which has been achieved well before the set time with the project being part of a larger solar power plant tender floated by GUVNL for the procurement of solar power from different solar photovoltaic plants across India.

Project Background and Award Details

KPI Green Energy had received the L rigid letter under Request for Selection, which was RFS No. GUVNL/500 MW/Solar (Phase-XXIV), dated 15th March 2024. GUVNL had floated the tender for a total capacity of 500 MW. It has given allocation through a competitive bidding process.

The company said the commissioned capacity forms part of the 250 MW AC (350 MW DC) solar photovoltaic project awarded to it under this auction framework.

Project Timeline and Execution Progress

  • Project awarded to KPI Green Energy in March 2025
  • First phase commissioned in approximately 11 months
  • Overall contractual completion timeline extends till October 2026
  • Remaining capacity expected to be executed at a similar pace

According to the company, the project is progressing in line with planned execution milestones, with a continued focus on maintaining efficiency, quality standards, and timely delivery.

Tariffs and Allocation Structure

GUVNL had offered the project capacity with a greenshoe option to all the selected bidders. KPI Green Energy won its allotment at a tariff of ₹ 2.67 per kWh. Other winners in the auction included :

  • Avaada Energy – ₹2.68/kWh
  • Solarcraft Power India–BluPine – ₹2.69/kWh
  • Hinduja Renewables – ₹2.72/kWh
  • NRC Industries – ₹2.72/kWh

Under the bucket-filling method, capacity allocation was as follows:

  • KPI Green Energy – 120 MW
  • Avaada Energy – 200 MW
  • Hinduja Renewables – 130 MW
  • Solarcraft Power India–BluPine – 40 MW
  • NRC Industries – 10 MW

With early commissioning already achieved, KPI Green Energy has reinforced its execution capabilities and continues to strengthen its position in India’s expanding utility-scale solar power market.

whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
GUVNL India News KPI Green Energy solar photovoltaic Solar Power Project
Manshi
  • Website

I'm journalism graduate with professional experience working across different news websites. I have been involved in news reporting, content writing, and digital media coverage, which has helped me develop a strong understanding of current affairs and storytelling. Currently, I am working with Battery Magazine, where I continue to create accurate, engaging, and reader-focused news content.

Keep Reading

Indofast Energy, Hala Mobility Target 40,000 EVs With Battery Swapping by March 2027

Indofast Energy, Hala Mobility Target 40,000 EVs With Battery Swapping by March 2027

Wärtsilä Reports Half-year Financial Results

Wärtsilä Reports Half-year Financial Results

KPI Green Commissions 200 MW Solar Capacity, Secures Charging Approval for 100 MW MAHAGENCO Project

KPI Green Commissions 200 MW Solar Capacity, Secures Charging Approval for 100 MW MAHAGENCO Project

Comments are closed.

Renewable energy
Indofast Energy, Hala Mobility Target 40,000 EVs With Battery Swapping by March 2027

Indofast Energy, Hala Mobility Target 40,000 EVs With Battery Swapping by March 2027

July 21, 2026
Wärtsilä Reports Half-year Financial Results

Wärtsilä Reports Half-year Financial Results

July 21, 2026
KPI Green Commissions 200 MW Solar Capacity, Secures Charging Approval for 100 MW MAHAGENCO Project

KPI Green Commissions 200 MW Solar Capacity, Secures Charging Approval for 100 MW MAHAGENCO Project

July 21, 2026
Smarten Power Systems, an Indian provider of solar energy and power backup solutions for both residential and commercial customers, released its business report for the quarter that concluded on June 30, 2026 (Q1 FY2026–27). Operational advancements in sales, distribution, manufacturing, and infrastructure characterised the quarter.

Smarten Power Systems Released its Business Report Q1 FY27 Sells 1.18 Lakh Units and Adds 32 Distributors in Nine States

July 21, 2026
Batteries
Fox ESS Launches POWER BEAST C&I Energy Storage System in Australia

Fox ESS Launches POWER BEAST C&I Energy Storage System in Australia

July 21, 2026
Adani Electricity Mumbai Gets Approval for 750 MW Round-the-Clock Renewable Power Procurement

Adani Electricity Mumbai Gets Approval for 750 MW Round-the-Clock Renewable Power Procurement

July 21, 2026
Graphite One Advances US Battery Supply Chain With Ohio Anode Material Plant

Graphite One Advances US Battery Supply Chain With Ohio Anode Material Plant

July 21, 2026
Delectrik 3 MWH Vanadium Redox Flow Battery Installation at Greater Noida, India Delectrik’s 3 MWH Vanadium Redox Flow Battery Installation at Greater Noida, India

Delectrik to Deploy India’s First 100 MWh Utility-Scale Vanadium Flow Battery

July 21, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.