Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Tenders » Tamil Nadu Floats Major 375 MW Battery Storage Tender to Boost Renewable Integration
Tenders

Tamil Nadu Floats Major 375 MW Battery Storage Tender to Boost Renewable Integration

PrakashBy PrakashNovember 18, 20252 Mins Read
Facebook Twitter LinkedIn WhatsApp
Trina Storage Launches Elementa 3, Advanced Utility-Scale Energy Storage Solution

Tamil Nadu has launched one of its largest standalone battery energy storage system (BESS) tenders, inviting developers to set up 375 MW / 1,500 MWh of utility-scale storage across seven strategic locations. Issued by the Chief Engineer, Renewable & Clean Energy Department (TANGEDCO), the tender aims to strengthen grid flexibility, manage peak demand, and support renewable integration. Bids will be submitted through tariff-based global competitive bidding, backed by significant central Viability Gap Funding (VGF) support.

Tender Overview

  • Total BESS Capacity: 375 MW / 1,500 MWh
  • Bidding Route: Tariff-based Global Competitive Bidding (e-Reverse Auction)
  • Bid Size: Minimum 25 MW/100 MWh
  • Maximum Allocation per Bidder: 175 MW/700 MWh
  • Issuing Authority: Chief Engineer, Renewable & Clean Energy Department, TANGEDCO
  • VGF Support: ₹18 lakh/MWh under the Power System Development Fund

Project Locations

BESS installations will be connected to TANTRANSCO substations located in:

  • Coimbatore
  • Tirunelveli
  • Trichy
  • Madurai
  • And other designated sites

TANTRANSCO will provide “Right to Use” land at a nominal cost of ₹1 per project per year.

Technical Specifications

  • Daily Cycling Requirement: 1.5 cycles per day
  • C-Rate: Minimum 0.25 C
  • Architecture: Modular blocks of

25 MW / 100 MWh to

50 MW / 200 MWh

Systems must support peak load shifting and renewable balancing.

Key Dates & Bid Conditions

Pre-Bid Meeting: 24 November 2025

Bid Submission Window: 05 December – 22 December 2025

Bidding Process: Two-phase competitive bidding with e-reverse auction

VGF Disbursement:

  • 20% at financial closure
  • 50% at COD
  • 30% after one year of successful operation

Eligibility & Requirements

Developer Eligibility

  • Open to global participants under tariff-based competitive bidding.
  • Developers can bid for modular blocks but must meet technical & financial criteria.

Scope of Work Includes:

  • Supply, installation & commissioning of standalone BESS
  • Energy management & control systems
  • Grid integration with TANTRANSCO
  • Compliance with cycling and C-rate requirements
  • Long-term performance obligations
Capacity 375 MW / 1,500 MWh
Location Coimbatore, Tirunelveli, Trichy, Madurai And other designated sites
Last Date 22/12/2025
whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
battery storage BESS projects clean energy Power System Development Fund renewable energy Tantransco Viability Gap Funding
Prakash
  • Website
  • LinkedIn

I am a Junior Journalist with experience in researching, reporting, and creating engaging content across diverse topics and platforms. My work has strengthened my skills in communication, relationship building, and understanding people, while also honing my organisational and problem-solving abilities.

Keep Reading

India’s Clean Energy Sector

India’s Clean Energy Workforce Grows by 6.6 Lakh, Rooftop Solar Leads Job Creation

SJVN Flags

SJVN Flags Renewable Power Demand Gap Amid Rising Capacity Additions

Consultative Committee Meeting

Consultative Committee Meeting of Ministry of Power Held in Chandigarh

Comments are closed.

Renewable energy
IIT Guwahati

IIT Guwahati Develops Perovskite Technology Achieving 25.73% Solar Cell Efficiency

June 4, 2026
India’s Clean Energy Sector

India’s Clean Energy Workforce Grows by 6.6 Lakh, Rooftop Solar Leads Job Creation

June 4, 2026
SJVN Flags

SJVN Flags Renewable Power Demand Gap Amid Rising Capacity Additions

June 4, 2026
Kyro Capital

Kyro Capital Launches ₹100 Crore Pre-IPO Fund Targeting Renewable Energy and Growth Sectors

June 3, 2026
Batteries
Advait Energy Secures 150 MW/300 MWh BESS Project from GUVNL

Advait Energy Secures 150 MW/300 MWh BESS Project from GUVNL

June 4, 2026
cylib and Vianode

cylib and Vianode Partner to Advance Recycled Graphite for EV Batteries

June 4, 2026
Trina Storage

Trina Storage Wins 160 MWh Ultra-High Voltage Battery Project in Japan’s Kyushu Region

June 3, 2026
Hoymiles Launches AI-Powered HiBattery 4020 Home Energy Storage Series

Hoymiles Launches AI-Powered HiBattery 4020 Home Energy Storage Series

June 3, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.