Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Tenders » GUVNL Launches 2 GW / 4 GWh BESS Tender in Gujarat with ₹18 L/MWh VGF Support
Tenders

GUVNL Launches 2 GW / 4 GWh BESS Tender in Gujarat with ₹18 L/MWh VGF Support

Shweta KumariBy Shweta KumariJuly 25, 20252 Mins Read
Facebook Twitter LinkedIn WhatsApp
GUVNL Launches 2 GW / 4 GWh BESS Tender in Gujarat

Gujarat Urja Vikas Nigam Ltd (GUVNL) has officially issued a tender on July 23, 2025 (RfS No. GUVNL/BESS/Phase VII) for the development of 2,000 MW / 4,000 MWh standalone Battery Energy Storage Systems (BESS) across Gujarat under a tariff-based competitive bidding process supported by the Power System Development Fund (PSDF) with Viability Gap Funding (VGF) assistance.

Key Highlights:

Capacity & Structure: BESS capacity allocated as 2 GW × 2-hour systems across 12 Gujarat STU substations—aggregate 4 GWh under the “Build-Own-Operate” model.

VGF Subsidy: Government support pegged at ₹18 lakh per MWh (₹180 crore per 100 MWh), capped per bidder and disbursed as 20% at financial closure, 50% at COD, and 30% one year post-COD.

Eligibility & Technical Requirements:

Minimum Bid Size: 100 MWh (50 MW × 2 hours) and multiples thereafter.

Eligibility: Minimum credentials include commissioning 1 MW power plant (renewable or conventional) or 10 MWh BESS capacity. Net worth requirement: ₹74 lakh per MW (FY 2024‑25 or prior 7 days).

Performance Standards: ≥ 85% round-trip efficiency, ≥ 95% annual system availability, and two full charge–discharge cycles daily.

Timeline & Process:

  • Query Deadline: 8 August 2025
  • Pre-bid Meeting: 13 August 2025 (via virtual conference)
  • Bid Submission: 11 September 2025
  • Technical & Commercial Evaluation: Mid-September shortlist ahead of reverse auction phase.

Tender Scope & Grid Attachment:

BESS projects to be connected at 12 predefined substations under GETCO’s transmission network.

Bidders are responsible for identifying land and establishing grid interconnections at their own cost; no merchant capacity allowed—projects will serve GUVNL on-demand dispatch requirements.

Significance:

This is Phase VII of GUVNL’s scalable BESS program, following earlier tenders under Phase IV (400 MW / 800 MWh) and Phase V–VI expansions.

The large-scale nature of this tender underscores GUVNL’s ambition to integrate renewable energy and improve grid flexibility with dispatchable capacity.

Strategic Insights

Investor appeal: Generous VGF and mandated performance metrics are likely to attract major developers and institutional interest.

Market signaling: GUVNL’s repeated BESS phases demonstrate Gujarat’s clear pathway toward utility-scale storage leadership.

Technical maturity: Enforcing ≥ 85% round-trip efficiency and ≥ 95% availability highlights a push for high-quality system deployment.

Entry constraints: Rigorous eligibility criteria—including financial and operational thresholds—ensure only credible players participate.

Capacity 2,000 MW / 4,000 MWh standalone BESS
Location Gujarat, across 12 GETCO substations
Last Date 11/09/2025
Results Tech-commercial bids will open on September 17, 2025 (results expected post reverse auction)
whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
battery storage BESS India clean tech energy storage energy transition GUVNL renewable energy
Shweta Kumari
  • Website
  • LinkedIn

Sub-editor by profession. Love for words and storytelling, where every word narrates a story. Shaping stories in a world powered by electrons—where lithium meets logic, and every spark tells a tale of innovation, sustainability, and our electrified future.

Keep Reading

JA Expands Solar-Plus-Storage Solutions Across Europe

JA Expands Solar-Plus-Storage Solutions Across Europe

JSW Energy Crosses 15 GW Capacity Milestone

JSW Energy Crosses 15 GW Capacity Milestone, Adds 1,572 MW in FY27

SPML Infra Marks BESS Milestone as Indigenous 104.4 kWh Battery Pack

SPML Infra Marks BESS Milestone as Indigenous 104.4 kWh Battery Pack Clears Global Tests

Comments are closed.

Renewable energy
India intends to Mandatory 2-hour battery storage

India intends to Mandatory 2-hour battery storage for new wind and solar installations

September 4, 2026
JA Expands Solar-Plus-Storage Solutions Across Europe

JA Expands Solar-Plus-Storage Solutions Across Europe

September 4, 2026
JSW Energy Crosses 15 GW Capacity Milestone

JSW Energy Crosses 15 GW Capacity Milestone, Adds 1,572 MW in FY27

September 4, 2026
SPML Infra Marks BESS Milestone as Indigenous 104.4 kWh Battery Pack

SPML Infra Marks BESS Milestone as Indigenous 104.4 kWh Battery Pack Clears Global Tests

September 4, 2026
Batteries
TCL Takes Its Energy Vision from Industry to Home

TCL Takes Its Energy Vision from Industry to Home at IFA 2026

September 4, 2026
Chery Set to Begin Solid-State Battery

Chery Set to Begin Solid-State Battery Road Tests in 2027

September 3, 2026
Hoymiles is Ready to Power the UK's New Plug-in Solar Era

Hoymiles Supports UK’s New Plug-in Solar Era with DIY Solar Solutions

September 3, 2026
Cosmic PV Power Clears SEBI Hurdle for Rs 640 Crore IPO

Cosmic PV Power Clears SEBI Hurdle for Rs 640 Crore IPO, Plans 1.1 GW TOPCon Cell Plant

September 3, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.