Power Grid Corporation of India Limited (POWERGRID) has announced the successful commissioning of the “Transmission System for Evacuation of Power from potential RE zone in Khavda Area of Gujarat under Phase IV (7 GW) – Part E4”.
The announcement was made through a regulatory filing submitted to the National Stock Exchange of India Limited (NSE) and BSE Limited.
The disclosure was made in accordance with Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, as amended. According to the filing, the project has been commissioned with effect from June 21, 2026, in terms of Regulation 5(1) of the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, 2024, and Regulation 27(1)(c)(i) of the Central Electricity Regulatory Commission (Indian Electricity Grid Code) Regulations, 2023.
POWERGRID further stated that the Date of Commercial Operation (DOCO) dated July 13, 2026, was received via email on July 14, 2026. The disclosure was submitted under Reference: NSE Scrip ID – POWERGRID; BSE Scrip Code – 532898; ISIN – INE752E01010 and was filed for the information and record of the stock exchanges.
Power Grid Corporation of India Limited (POWERGRID) is a Government of India enterprise engaged in power transmission. The company develops, operates and maintains transmission infrastructure across the country and plays a key role in strengthening India’s electricity grid.
Anjana Luthra, Company Secretary & Compliance Officer, Power Grid Corporation of India Limited, signed the regulatory communication.