Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Renewable energy » CERC Revises Connectivity Rules for Renewable Energy and Energy Storage Projects
Renewable energy

CERC Revises Connectivity Rules for Renewable Energy and Energy Storage Projects

Shivangi GuptaBy Shivangi GuptaNovember 13, 20262 Mins Read
Facebook Twitter LinkedIn WhatsApp
CERC Revises Connectivity Rules for Renewable Energy and Energy Storage Projects

The Central Electricity Regulatory Commission (CERC) has notified the Fourth Amendment to the Connectivity and General Network Access (GNA) Regulations, 2026, introducing changes to connectivity withdrawal, bank guarantee release, renewable energy and energy storage access, and transmission network utilisation.

The amendment allows entities to withdraw their entire connectivity quantum if the final connectivity grant is delayed by two years or more. Such entities must submit withdrawal applications within a 45-day window. Upon acceptance, applicable bank guarantees will be returned, while the application fee will be forfeited.

The revised regulations also reduce the timeline for releasing bank guarantees associated with generation capacity. These guarantees can now be released within one week after completion of one year from the declaration of the commercial operation date (COD), replacing the earlier five-year period.

For renewable energy generating stations and energy storage systems (ESS) with capacities of 50 MW and above, the amendment introduces connectivity provisions for non-solar hours at substations where transmission margins are available. Energy storage systems seeking such connectivity must have a minimum energy capacity equivalent to twice their power capacity.

The amendment further recognises General Network Access (GNA) transfers following asset acquisitions and permits large consumers to obtain dual connectivity to inter-state and intra-state transmission networks, subject to a minimum connectivity quantum of 50 MW.

The regulatory changes are expected to improve flexibility in transmission connectivity, facilitate renewable energy and energy storage integration, and support more efficient utilisation of India’s inter-state transmission network.

whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
CERC energy storage GNA Regulations India News renewable energy Transmission Connectivity
Shivangi Gupta
  • Website

Shivangi Gupta is a journalist passionate about writing and delivering accurate, clear, and informative news stories across a wide range of topics.

Keep Reading

Loom Secures 1 MWh Solar-Plus-Storage Project for Rice Mill in Chhattisgarh

Loom Secures 1 MWh Solar-Plus-Storage Project for Rice Mill in Chhattisgarh

CleanMax Plans ₹50,000 Crore Investment in Andhra Pradesh for Renewable Energy and Pumped Storage

CleanMax Plans ₹50,000 Crore Investment in Andhra Pradesh for Renewable Energy and Pumped Storage

HiTHIUM Hosts Inaugural Global Energy Storage Colloquium in Xiamen

HiTHIUM Hosts Inaugural Global Energy Storage Colloquium in Xiamen

Leave A Reply Cancel Reply

nine − four =

Renewable energy
CleanMax Plans ₹50,000 Crore Investment in Andhra Pradesh for Renewable Energy and Pumped Storage

CleanMax Plans ₹50,000 Crore Investment in Andhra Pradesh for Renewable Energy and Pumped Storage

November 13, 2026
Sungrow Expands Into Residential Battery Storage Amid Profit Pressure

Sungrow Expands Into Residential Battery Storage Amid Profit Pressure

November 13, 2026
ReNew Announces ₹80,000 Crore Investment in Andhra Pradesh for Green Data Centre and Solar Manufacturing

ReNew Announces ₹80,000 Crore Investment in Andhra Pradesh for Green Data Centre and Solar Manufacturing

November 13, 2026
Fourth Partner Energy Signs 45 MW Wind-Solar Hybrid PPA with GACL

Fourth Partner Energy Signs 45 MW Wind-Solar Hybrid PPA with GACL

November 13, 2026
Batteries
Loom Secures 1 MWh Solar-Plus-Storage Project for Rice Mill in Chhattisgarh

Loom Secures 1 MWh Solar-Plus-Storage Project for Rice Mill in Chhattisgarh

November 13, 2026
HiTHIUM Hosts Inaugural Global Energy Storage Colloquium in Xiamen

HiTHIUM Hosts Inaugural Global Energy Storage Colloquium in Xiamen

November 13, 2026
KP Group Plans ₹5,000 Crore Investment in 10 GWh Battery Cell Manufacturing

KP Group Plans ₹5,000 Crore Investment in 10 GWh Battery Cell Manufacturing

November 13, 2026
Soneil Spark Unveils Mobile BESS, Bringing Power Infrastructure on Wheels at RE+ 2026

Soneil Spark Unveils Mobile BESS, Bringing Power Infrastructure on Wheels at RE+ 2026

November 13, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.