The Central Electricity Regulatory Commission (CERC) has allowed Chhattisgarh State Power Distribution Company Limited (CSPDCL) to amend its petition against Adani Solar Energy Jaisalmer One Private Limited over an ₹85.28 crore claim related to Safeguard Duty (SGD) on imported solar cells. The commission issued its order on November 19, 2026, permitting the amendment while keeping the original claim amount unchanged.
The dispute concerns the applicability of safeguard duty on imported solar cells used in solar power projects. When Adani Solar submitted its bid on November 20, 2018, the applicable safeguard duty was 15%. CSPDCL had initially referred to a subsequent government notification dated July 29, 2020, in its petition but later sought to include an earlier notification dated July 30, 2018.
CSPDCL stated that the omission of the 2018 notification from its formal submissions was an error, as the notification had already been mentioned in the original petition.
Background of the Safeguard Duty Dispute
CSPDCL procures electricity from Adani Solar’s 450 MW solar power project in Rajasthan through the Solar Energy Corporation of India (SECI).
The dispute arose after the safeguard duty on imported solar cells was withdrawn with effect from July 30, 2021. CSPDCL considers the withdrawal a Change in Law event and argues that the resulting reduction in project costs should be passed on to the procuring distribution company.
Based on this position, CSPDCL is seeking either a reduction in the applicable power tariff or direct compensation of ₹85.28 crore, along with applicable interest.
The company maintains that the removal of the duty reduced the costs associated with solar module procurement and that the resulting financial benefit should be reflected in the power purchase arrangement.
Adani Solar Raises Objections
Adani Solar opposed CSPDCL’s request to amend the petition and sought its rejection, raising concerns over the timing and basis of the claim.
Its objections included the argument that the amendment request was filed beyond the three-year limitation period. Adani Solar also maintained that the safeguard duty notification had a specified validity period, making its eventual expiry a known development rather than an unexpected regulatory change.
Additionally, Adani Solar argued that it procured solar modules only from October 2021 and, therefore, had not paid the safeguard duty or received any financial benefit from its withdrawal. It also questioned the claim’s reliance on assumptions rather than actual procurement costs.
CERC Allows Amendment, Main Dispute Remains Open
While considering the matter, CERC observed that the July 30, 2018 notification was already referred to in CSPDCL’s original petition. Accordingly, the commission treated the proposed modification as a clarification rather than the introduction of an entirely new claim.
The commission also held that allowing the amendment would not cause prejudice to Adani Solar. It described the objections raised by the company as hyper-technical and clarified that Adani Solar would retain the opportunity to raise its arguments during the hearing of the main petition.
The latest order does not determine whether CSPDCL is entitled to the claimed compensation. The questions surrounding the applicability of the Change in Law provision, the actual financial impact of the safeguard duty withdrawal and the ₹85.28 crore compensation claim will be considered in the substantive proceedings.
The development keeps the regulatory dispute between CSPDCL and Adani Solar open, with the final outcome expected to determine whether the financial benefits arising from the withdrawal of safeguard duty should be passed on to the power procurer.