Rajasthan Energy Minister Heeralal Nagar has directed developers to complete 6,000 MWh of battery energy storage system (BESS) projects across the state between December 2026 and November 2027. The minister has also warned of strict action against developers who fail to meet the prescribed deadlines.
The directions were issued during a review meeting held at Vidyut Bhawan in Jaipur on November 24, 2026. The meeting reviewed the progress of BESS projects awarded to developers selected through NTPC Vidyut Vyapar Nigam (NVVN).
Officials from the Rajasthan Energy Department, Rajasthan Rajya Vidyut Utpadan Nigam and project developers participated in the meeting. Discussions covered construction progress, project timelines, land availability, grid connectivity and pending regulatory approvals.
Rajasthan Reviews 6,000 MWh BESS Project Timeline
During the meeting, Nagar directed JSW to complete its 250 MWh BESS projects at Giral and Suratgarh by December 2026. The completion deadlines for the remaining projects range from December 29, 2026, to November 7, 2027.
The minister instructed Rajasthan Rajya Vidyut Utpadan Nigam officials to regularly monitor project progress and ensure that developers adhere to their respective commissioning schedules.
He also assured developers that the state government would provide the necessary coordination and support to resolve implementation-related challenges. However, he warned that strict action would be taken against developers responsible for delays.
BESS Projects Awarded Under VGF and PSDF Schemes
The 6,000 MWh storage deployment includes projects awarded under the Central Government’s Viability Gap Funding (VGF) and Power System Development Fund (PSDF) schemes.
The awarded capacities are divided into the following configurations:
-
State component: 1,000 MWh with a two-hour, two-cycle configuration.
-
Central component: 1,000 MWh with a two-hour, two-cycle configuration.
-
PSDF component: 2,000 MWh with a two-hour, two-cycle configuration.
-
PSDF component: 2,000 MWh with a four-hour, one-cycle configuration.
The awarded tariffs ranged from ₹1.77 lakh to ₹2.85 lakh per MW per month. According to the state, these rates were the lowest in the country at the time of procurement.
BESS Deployment to Support Renewable Energy Integration
The planned BESS installations are expected to strengthen Rajasthan’s electricity storage infrastructure and support the integration of renewable energy into the state’s power grid.
Once commissioned, the projects will help improve grid stability, manage fluctuations in renewable energy generation and provide reliable electricity during peak demand periods. Battery storage is also expected to support the availability of electricity at lower rates during periods of high demand.
The state’s latest directive highlights its focus on accelerating large-scale BESS deployment and ensuring timely execution of awarded energy storage projects.