Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Batteries » Battery Manufacturing (BESS) » UPERC Approves ₹6.46/kWh Tariff for 125 MW/500 MWh BESS Project in Uttar Pradesh
Battery Manufacturing (BESS)

UPERC Approves ₹6.46/kWh Tariff for 125 MW/500 MWh BESS Project in Uttar Pradesh

Shivangi GuptaBy Shivangi GuptaNovember 26, 20263 Mins Read
Facebook Twitter LinkedIn WhatsApp
UPERC Approves ₹6.46/kWh Tariff for 125 MW/500 MWh BESS Project in Uttar Pradesh

The Uttar Pradesh Electricity Regulatory Commission (UPERC) has approved a tariff of ₹6.46 per kWh for procurement of 125 MW/500 MWh of standalone battery energy storage system (BESS) capacity from MKC Kashivisvanath Ji Energy Private Limited. The approval covers a 15-year period under a Battery Energy Discharge Purchase Agreement (BEDPA) signed with Uttar Pradesh Power Corporation Limited (UPPCL) on June 3, 2026.

In its order dated November 19, 2026, under Petition No. 2403 of 2026, the Commission also approved the BEDPA between UPPCL and the project developer. The project is part of Uttar Pradesh’s broader procurement plan for 375 MW/1,500 MWh of standalone BESS capacity with Viability Gap Funding (VGF) support under the Power System Development Fund (PSDF).

Pt-no-2403of2026UPPCL-19-11-2026-PDF1120202653045PM.pdf

BESS Capacity Awarded Through Competitive Bidding

UPPCL conducted the procurement through a Tariff-Based Competitive Bidding (TBCB) process under the Build, Own and Operate (BOO) model. The tender received bids from 13 developers, of which 12 were found technically qualified. Following the financial bid evaluation and e-reverse auction conducted on May 2, 2026, three developers were selected for the total procurement capacity of 375 MW.

The selected developers and their final tariffs were:

Selected developer Final tariff Allocated capacity
KCC BuildCon Pvt. Ltd. ₹6.45/kWh 187.5 MW
Agastya Green Energy Ltd. ₹6.45/kWh 62.5 MW
MKC Green Energy Ltd. ₹6.46/kWh 125 MW
Total 375 MW

MKC Green Energy was initially awarded 125 MW under its parent company before the project was assigned to its special purpose vehicle (SPV), MKC Kashivisvanath Ji Energy Private Limited. The BEDPA was subsequently executed for 125 MW/500 MWh at ₹6.46/kWh.

Project Timeline and Implementation

According to the approved BEDPA, the project has a scheduled commissioning date of December 7, 2027. The agreement requires the developer to achieve financial closure within six months and scheduled commissioning within 18 months from the effective date of the agreement.

The project will receive VGF support under the Ministry of Power’s PSDF scheme. The selected developer is also required to provide performance bank guarantees and meet the commissioning and operational requirements specified in the tender documents.

UPERC’s Approval and Project Significance

UPERC observed that the discovered tariff of ₹6.46/kWh was competitive compared with tariffs in earlier BESS procurement processes. The Commission noted that the project would support renewable energy integration, help meet peak electricity demand and provide greater flexibility in managing Uttar Pradesh’s power requirements.

The Commission also highlighted the role of standalone BESS in improving grid stability, power quality and resource adequacy as renewable energy penetration increases.

With this approval, UPPCL can proceed with the implementation of the 125 MW/500 MWh project under the approved tariff and 15-year agreement.

whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
Battery Energy Storage System BESS India News MKC Green Energy UPERC UPPCL
Shivangi Gupta
  • Website

Shivangi Gupta is a journalist passionate about writing and delivering accurate, clear, and informative news stories across a wide range of topics.

Keep Reading

Power Ministry Proposes Mandatory Battery Storage for Rooftop Solar Systems Above 10 kW

Power Ministry Proposes Mandatory Battery Storage for Rooftop Solar Systems Above 10 kW

ACME Solar Commissions 255.12 MWh Battery Storage System for NHPC Renewable Energy Project

ACME Solar Commissions 255.12 MWh Battery Storage System for NHPC Renewable Energy Project

Hindustan Zinc and IIT Madras Develop 1 kWh Zinc-Air Battery for Electric Three-Wheeler

Hindustan Zinc and IIT Madras Develop 1 kWh Zinc-Air Battery for Electric Three-Wheeler

Leave A Reply Cancel Reply

one + five =

Renewable energy
ACME Solar Commissions 255.12 MWh Battery Storage System for NHPC Renewable Energy Project

ACME Solar Commissions 255.12 MWh Battery Storage System for NHPC Renewable Energy Project

November 26, 2026
Diamond Power Secures ₹488 Crore Orders for Conductors for Bhadla-Fatehpur HVDC Renewable Energy Corridor

Diamond Power Secures ₹488 Crore Orders for Conductors for Bhadla-Fatehpur HVDC Renewable Energy Corridor

November 26, 2026
Cosmic PV Power Secures Second 200 MW Solar Module Order from Zetwerk, Plans 2 GW BESS Assembly Line

Cosmic PV Power Secures Second 200 MW Solar Module Order from Zetwerk, Plans 2 GW BESS Assembly Line

November 26, 2026
Vena Energy Secures US$113 Million Green Loan to Refinance 114 MW Renewable Energy Portfolio in Indonesia

Vena Energy Secures US$113 Million Green Loan to Refinance 114 MW Renewable Energy Portfolio in Indonesia

November 26, 2026
Batteries
Power Ministry Proposes Mandatory Battery Storage for Rooftop Solar Systems Above 10 kW

Power Ministry Proposes Mandatory Battery Storage for Rooftop Solar Systems Above 10 kW

November 26, 2026
Hindustan Zinc and IIT Madras Develop 1 kWh Zinc-Air Battery for Electric Three-Wheeler

Hindustan Zinc and IIT Madras Develop 1 kWh Zinc-Air Battery for Electric Three-Wheeler

November 26, 2026
Rajasthan Sets November 2027 Deadline for Completion of 6,000 MWh BESS Projects

Rajasthan Sets November 2027 Deadline for Completion of 6,000 MWh BESS Projects

November 26, 2026
UPERC Approves ₹6.46/kWh Tariff for 125 MW/500 MWh BESS Project in Uttar Pradesh

UPERC Approves ₹6.46/kWh Tariff for 125 MW/500 MWh BESS Project in Uttar Pradesh

November 26, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.