Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Renewable energy » CERC Rejects Phase-Wise Commissioning Request for Continuum’s 36 MW Wind Project
Renewable energy

CERC Rejects Phase-Wise Commissioning Request for Continuum’s 36 MW Wind Project

Sanjana NegiBy Sanjana NegiJuly 1, 20263 Mins Read
Facebook Twitter LinkedIn WhatsApp
CERC Rejects

The Central Electricity Regulatory Commission (CERC) has rejected a petition filed by Continuum Power Trading Private Limited (CPTPL) seeking permission to commission its 36 MW Meghpar wind power project in Kutch, Gujarat, in phases. The Commission ruled that developers must complete trial runs for the entire capacity for which connectivity has been granted before commissioning the project.

Continuum had requested relaxation of Regulation 22(3)(c) of the Indian Electricity Grid Code (IEGC), 2023, to allow commissioning of the project in smaller batches of at least 5 MW as individual wind turbine generators (WTGs) became technically ready. The company argued that waiting for the complete 36 MW capacity would delay operations and prevent early power generation.

The developer stated that delays in obtaining connectivity approval from the Central Transmission Utility of India Ltd. (CTUIL) affected its commissioning timeline. Continuum had applied for connectivity on July 20, 2024, with a scheduled commercial operation date (SCOD) of March 31, 2025. However, the in-principle connectivity grant was issued on May 23, 2025, followed by the final grant on August 14, 2025.

Continuum argued that the delayed connectivity and deferred start date were beyond its control and should be treated as a force majeure situation. The company informed CERC that around 21 MW of the project capacity was ready for commissioning and that allowing phased commissioning would help avoid renewable energy assets remaining idle. It also stated that early commissioning could allow electricity sales through power exchanges and help maintain eligibility for transmission charge benefits.

CERC, however, rejected these arguments and stated that connectivity can only be provided from the date when the transmission system is available or expected to become available. The Commission observed that the delay in connectivity approval did not qualify as a force majeure event.

The regulator further noted that even if the in-principle connectivity had been granted earlier, the developer would still have had limited time to complete the project. CERC stated that the developer had sufficient time after receiving the final connectivity approval but failed to complete the project within the available period.

On the regulatory requirement, CERC clarified that Regulation 22(3)(c) of IEGC, 2023 requires a trial run for the complete capacity where connectivity has been granted under the General Network Access (GNA) framework. Since Continuum received connectivity for 36 MW, the trial run must be conducted for the entire 36 MW capacity in a single batch.

The Commission also noted that developers are aware of these requirements while applying for connectivity and found no reason to relax the regulation in this case. Accordingly, Continuum’s petition seeking permission for phased commissioning was dismissed.

The order reinforces CERC’s strict approach towards grid code compliance and indicates that delays in connectivity approvals or commercial considerations will not automatically justify relaxation of commissioning and trial run requirements for renewable energy projects.

whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
CERC GNA India News power generation renewable energy projects
Sanjana Negi
  • Website

News contributor at The Battery Magazine. I write on the latest developments in battery technology, energy storage solutions, and power innovations. Committed to delivering accurate and timely updates from the world of batteries.

Keep Reading

How does a home battery manage to store solar energy for use at night?

How does a home battery manage to store solar energy for use at night?

How Do Electric Vehicle Batteries Work?

How Do Electric Vehicle Batteries Work?

How Battery Storage Helps India Make Better Use of Solar Power

How Battery Storage Helps India Make Better Use of Solar Power

Leave A Reply Cancel Reply

eighteen − 11 =

Renewable energy

Infineon and Wolfspeed Sign Multi-Year Agreement for 200 mm SiC Wafer Supply

October 16, 2026
NTPC and Africa50 Join Hands to Develop Power Generation and Cross-Border Electricity Projects in Africa

NTPC and Africa50 Join Hands to Develop Power Generation and Cross-Border Electricity Projects in Africa

October 16, 2026
Gujarat Inject (Kerala) Secures ₹6.25 Crore Solar Panel Order from Deon Energy

Gujarat Inject (Kerala) Secures ₹6.25 Crore Solar Panel Order from Deon Energy

October 16, 2026
Vikram Solar Wins 187 MW Module Supply Order for Solar Projects in Karnataka and Tamil Nadu

Vikram Solar Wins 187 MW Module Supply Order for Solar Projects in Karnataka and Tamil Nadu

October 16, 2026
Batteries
Wärtsilä to Deploy 35 MW/70 MWh Battery Storage System to Strengthen Aruba’s Power Grid

Wärtsilä to Deploy 35 MW/70 MWh Battery Storage System to Strengthen Aruba’s Power Grid

October 16, 2026

Changan and CATL Plan to Expand Joint Battery Manufacturing Capacity to 75 GWh

October 16, 2026
Philippines Reports Normal Power Supply Outlook as DOE Advances Battery Storage Capacity

Philippines Reports Normal Power Supply Outlook as DOE Advances Battery Storage Capacity

October 16, 2026
NTPC Invites Bids for 15 MW Floating Solar Project with 60 MWh BESS in Mauritius

NTPC Invites Bids for 15 MW Floating Solar Project with 60 MWh BESS in Mauritius

October 16, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.