The Central Electricity Regulatory Commission (CERC) has released a landmark ruling statement that signals a shift towards a more reality-based regulatory landscape. The Central Electricity Regulatory Commission (CERC) has reversed its connectivity revocation order pertaining to AWPL; this case establishes the principle that while timelines are important for regulating discipline of interconnected systems, timelines cannot be used to eliminate “common sense” or eliminate the ability of a project to proceed.
The case began when the Central Transmission Utility of India Limited (CTUIL) revoked AWPL’s 175 MW wind project connectivity in September 2025. The revocation was based on a technicality: the developer had failed to rectify minor discrepancies in land documentation within a strict 15-day “advisory” window.
The Errors:
These mistakes included small calculation revisions in land undertakings and the requirement to translate Gujarati lease deeds into Hindi or English.
Despite the project being at an advanced stage—with 100% of towers already erected—CTUIL moved to revoke connectivity and encash nearly ₹21.5 crore in bank guarantees.
The Commission’s intervention centered on the “Doctrine of Substantial Compliance”. CERC stated that AWPL has successfully fulfilled the “substance or essence” of the rule by obtaining the required land and finishing the physical infrastructure of the project. The Commission argued that strictly adhering to minor formalities like translation deadlines would lead to “hardship and injustice”.
The CERC emphasized that revoking connectivity for a nearly finished project would be “disproportionate”. Taking such rigorous step against the developer for a minor mistake would not only harm it but would also indirectly affect end consumers by delaying the supply of renewable energy.
Key Legal Takeaways
- Restoration of Connectivity: The CERC quashed the revocation letter and ordered the immediate restoration of AWPL’s 175 MW connectivity.
- Commissioning Activities: The developer is now permitted to proceed with First Time Charging (FTC) and trial operations.
- Financial Discipline: To maintain discipline, the Commission condoned the delay but imposed a penalty of 5% of the Land Bank Guarantee. This ensures that while flexibility is granted, delays still carry a cost.
- Protection of Bank Guarantees: The ruling criticized the “inadvertent” encashment of bank guarantees while the matter was sub judice, reinforcing that due process and interim protections must be respected.
This ruling provides a significant safety net for India’s renewable energy sector. It sends a clear message to transmission utilities that the goal of the General Network Access (GNA) framework is to facilitate energy transition, not to act as a hurdle for genuine developers. By balancing “Rules and Reality,” the CERC has ensured that technicalities will no longer derail the nation’s green energy progress.





