The Ministry of New & Renewable Energy (MNRE) has issued a significant order providing relief to renewable energy developers affected by delays due to legal proceedings involving the Great Indian Bustard (GIB). The directive, dated January 12, 2026, classifies these delays as a “Force Majeure” event, enabling extensions for project commissioning timelines and easing financial and operational risks.
The delays stem from Supreme Court case W.P.(C) 838/2019, which concerned the overhead laying of power transmission lines in GIB habitats across Rajasthan and Gujarat. An expert committee was formed to examine the ecological impact, and the final judgment was delivered on December 19, 2025. During the period from March 21, 2024, to December 19, 2025, many developers were unable to obtain approvals under Section 68 of the Electricity Act, 2003, necessary for project commissioning.
Key Provisions of the MNRE Order
Under the new guidelines, implementing agencies such as SECI, NTPC, NHPC, and SJVN are directed to grant extensions for the Scheduled Commissioning Date (SCD) for affected projects. The extension period is calculated from either the date a developer applied for Section 68 approval or March 21, 2024, whichever is later, until December 19, 2025. Projects with SCDs before March 21, 2024, or developers who did not apply for Section 68 approval are not eligible. Developers must submit formal applications with supporting documents and provide an undertaking to comply with Supreme Court and expert committee recommendations, including environmental safeguards for GIB habitats.
Operational and Financial Relief
The MNRE order encourages developers to pass benefits to EPC contractors, equipment suppliers, and OEMs. Agencies are required to extend intermediate milestone timelines in line with the overall extension. Additionally, the Ministry of Power and Central Transmission Utility (CTUIL) have been requested to extend connectivity, General Network Access (GNA), and continue Inter-State Transmission System (ISTS) waivers for the extended period, mitigating financial burden.
Sector Implications
This relief addresses significant uncertainties that stalled wind and solar projects in key regions. Reports indicated that as of June 2025, over 50 GW of renewable capacity faced grid-related delays, while FY25 saw a 42% shortfall in transmission additions. By granting extensions, MNRE aims to ensure project continuity, maintain investor confidence, and support India’s transition to clean energy while protecting endangered species.





