Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Tenders » UPCL Floats 41 MW/102.5 MWh Standalone Battery Storage Tender Across Uttarakhand
Tenders

UPCL Floats 41 MW/102.5 MWh Standalone Battery Storage Tender Across Uttarakhand

Shweta KumariBy Shweta KumariNovember 20, 20263 Mins Read
Facebook Twitter LinkedIn WhatsApp
UPCL Floats 41 MW/102.5 MWh Standalone Battery Storage Tender Across Uttarakhand

Uttarakhand Power Corporation Limited (UPCL) has invited bids for developing 41 MW/102.5 MWh of grid-connected standalone Battery Energy Storage Systems (BESS) across six substations in the state. Issued under Request for Proposal (RFP) No. CCP-I/49/2026-2027, the tender covers projects in Uttarkashi, Haridwar and Tehri districts and will be implemented under a capacity charge-based competitive bidding mechanism with Viability Gap Funding (VGF) support.

The RFP was issued on 17 November 2026, while the tender was published on the Uttarakhand government e-procurement portal on 18 November. The last date for bid submission is 4 December 2026, at 5:00 PM. UPCL has scheduled the pre-bid meeting for 26 November at 11:30 AM at its Dehradun office, with online participation also available.

BESS deployment across six substations

According to the tender document, the proposed 41 MW/102.5 MWh capacity will be distributed across the following locations:

District Substation Capacity
Uttarkashi Kalyani 10 MW/25 MWh
Uttarkashi Dhanarigaad 10 MW/25 MWh
Haridwar SIDCUL Sector 8 4 MW/10 MWh
Haridwar Jwalapur 2 6 MW/15 MWh
Haridwar New Manglaur 6 MW/15 MWh
Tehri Rajakhet 5 MW/12.5 MWh
Total Six substations 41 MW/102.5 MWh

The locations and capacities are tentative and may be revised by UPCL based on site surveys, land availability and load-flow requirements. The utility will provide land to selected developers on a Right-of-Use basis.

Two charge-discharge cycles daily

The selected Battery Energy Storage System Developers (BESSDs) will be responsible for designing, financing, supplying, installing, testing, commissioning, operating and maintaining the systems. The BESS installations must support two complete charge-discharge cycles daily, with 2.5 hours of discharge during morning peak hours and another 2.5 hours during evening peak hours.

The systems will connect to UPCL’s 33 kV distribution network through its 33/11 kV substations. The tender specifies a minimum annual system availability of 95%, with liquidated damages applicable for shortfalls. The storage systems are expected to support energy arbitrage, peak-load management and grid operations.
Cluster C (1)+3

VGF support and project execution

The tender refers to the Ministry of Power’s VGF guidelines issued on 9 June 2025. Under the approved arrangement, Uttarakhand has been allocated VGF support of ₹18 lakh per MWh for developing 500 MWh of BESS capacity through the Power System Development Fund (PSDF). The support is intended to be extended to eligible developers setting up storage projects in the state.

The selected developers will also be responsible for operation and maintenance over a 12-year period, including battery-system upkeep, insurance, overhauling and replacement of defective cells, inverters and other equipment. The RFP specifies that project installation, testing and commissioning must be completed within 12 months from the effective date of the Battery Energy Storage Purchase Agreement or handover of land, whichever occurs later.

The tender adds another standalone storage procurement to Uttarakhand’s efforts to strengthen its electricity network and manage peak demand through battery-based storage. By locating the systems at distribution substations, UPCL is seeking to use storage for local grid support as well as shifting electricity supply between off-peak and peak-demand periods.

Capacity 41 MW/102.5 MWh Standalone BESS
Location Uttarkashi, Haridwar and Tehri districts
Last Date 04/12/2026
whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
Battery Energy Storage System India News Peak Load Management Standalone BESS UPCL Uttarakhand Power Corporation Viability Gap Funding
Shweta Kumari
  • Website
  • LinkedIn

Sub-editor by profession. Love for words and storytelling, where every word narrates a story. Shaping stories in a world powered by electrons—where lithium meets logic, and every spark tells a tale of innovation, sustainability, and our electrified future.

Keep Reading

TrueRE Oriana Power Plans Five CBG Plants Across Three States

TrueRE Oriana Power Plans Five CBG Plants Across Three States

Bhutan Extends Chhukha Power Export Agreement with India

Bhutan, PTC India Extend Chhukha Hydropower Export Agreement Until 2031

KKR Takes Minority Stake in Gentari’s India Renewables Platform

KKR Takes Minority Stake in Gentari’s India Renewables Platform

Leave A Reply Cancel Reply

five + fifteen =

Renewable energy
TrueRE Oriana Power Plans Five CBG Plants Across Three States

TrueRE Oriana Power Plans Five CBG Plants Across Three States

November 20, 2026
Bhutan Extends Chhukha Power Export Agreement with India

Bhutan, PTC India Extend Chhukha Hydropower Export Agreement Until 2031

November 20, 2026
KKR Takes Minority Stake in Gentari’s India Renewables Platform

KKR Takes Minority Stake in Gentari’s India Renewables Platform

November 20, 2026
APTEL Scraps rs 0.50 Rate for Excess Wind Power

APTEL Orders Full Tariff Payment for Wind Power Beyond Normative CUF

November 20, 2026
Batteries
MULTIFIT Strengthens Its Solar and Battery Storage Portfolio

MULTIFIT Expands Solar Storage Portfolio with Hybrid Inverters and Integrated Battery Systems

November 20, 2026
Four Firms Advance Under Rare Earth Magnet Scheme

Coal India, ReNew Among Four Firms Advancing Under ₹7,280-Crore Rare Earth Magnet Scheme

November 20, 2026
Juniper Green Commissions 108.50 MWp Solar, 94.77 MWh BESS

Juniper Green Adds 108.50 MWp Solar and 94.77 MWh Storage to Portfolio

November 20, 2026
Midwest Energy Wins LoI for 1,200 MTPA Magnets

Midwest Energy Secures LoI for 1,200 MTPA Rare Earth Magnet Project Under Centre’s ₹7,280-Crore Scheme

November 20, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.