Uttarakhand Power Corporation Limited (UPCL) has invited bids for developing 41 MW/102.5 MWh of grid-connected standalone Battery Energy Storage Systems (BESS) across six substations in the state. Issued under Request for Proposal (RFP) No. CCP-I/49/2026-2027, the tender covers projects in Uttarkashi, Haridwar and Tehri districts and will be implemented under a capacity charge-based competitive bidding mechanism with Viability Gap Funding (VGF) support.
The RFP was issued on 17 November 2026, while the tender was published on the Uttarakhand government e-procurement portal on 18 November. The last date for bid submission is 4 December 2026, at 5:00 PM. UPCL has scheduled the pre-bid meeting for 26 November at 11:30 AM at its Dehradun office, with online participation also available.
BESS deployment across six substations
According to the tender document, the proposed 41 MW/102.5 MWh capacity will be distributed across the following locations:
| District | Substation | Capacity |
| Uttarkashi | Kalyani | 10 MW/25 MWh |
| Uttarkashi | Dhanarigaad | 10 MW/25 MWh |
| Haridwar | SIDCUL Sector 8 | 4 MW/10 MWh |
| Haridwar | Jwalapur 2 | 6 MW/15 MWh |
| Haridwar | New Manglaur | 6 MW/15 MWh |
| Tehri | Rajakhet | 5 MW/12.5 MWh |
| Total | Six substations | 41 MW/102.5 MWh |
The locations and capacities are tentative and may be revised by UPCL based on site surveys, land availability and load-flow requirements. The utility will provide land to selected developers on a Right-of-Use basis.
Two charge-discharge cycles daily
The selected Battery Energy Storage System Developers (BESSDs) will be responsible for designing, financing, supplying, installing, testing, commissioning, operating and maintaining the systems. The BESS installations must support two complete charge-discharge cycles daily, with 2.5 hours of discharge during morning peak hours and another 2.5 hours during evening peak hours.
The systems will connect to UPCL’s 33 kV distribution network through its 33/11 kV substations. The tender specifies a minimum annual system availability of 95%, with liquidated damages applicable for shortfalls. The storage systems are expected to support energy arbitrage, peak-load management and grid operations.
Cluster C (1)+3
VGF support and project execution
The tender refers to the Ministry of Power’s VGF guidelines issued on 9 June 2025. Under the approved arrangement, Uttarakhand has been allocated VGF support of ₹18 lakh per MWh for developing 500 MWh of BESS capacity through the Power System Development Fund (PSDF). The support is intended to be extended to eligible developers setting up storage projects in the state.
The selected developers will also be responsible for operation and maintenance over a 12-year period, including battery-system upkeep, insurance, overhauling and replacement of defective cells, inverters and other equipment. The RFP specifies that project installation, testing and commissioning must be completed within 12 months from the effective date of the Battery Energy Storage Purchase Agreement or handover of land, whichever occurs later.
The tender adds another standalone storage procurement to Uttarakhand’s efforts to strengthen its electricity network and manage peak demand through battery-based storage. By locating the systems at distribution substations, UPCL is seeking to use storage for local grid support as well as shifting electricity supply between off-peak and peak-demand periods.
| Capacity | 41 MW/102.5 MWh Standalone BESS |
| Location | Uttarkashi, Haridwar and Tehri districts |
| Last Date | 04/12/2026 |