Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Renewable energy » Utilities Cannot Deny Force Majeure Relief Despite Being Fully Aware Of Delays: APTEL
Renewable energy

Utilities Cannot Deny Force Majeure Relief Despite Being Fully Aware Of Delays: APTEL

Sanjana NegiBy Sanjana NegiMay 21, 20263 Mins Read
Facebook Twitter LinkedIn WhatsApp
APTEL

The Appellate Tribunal for Electricity (APTEL) has ruled that utilities and nodal agencies cannot deny relief to renewable energy developers over delayed or improper notices when they were already aware of the issue and were involved in resolving it.

The ruling came in a batch of appeals filed by Punjab Energy Development Agency (PEDA) challenging Punjab State Electricity Regulatory Commission’s (PSERC) orders granting extension of scheduled commissioning dates (SCOD) to solar projects developed by Mihit Solar Pvt. Ltd. under Punjab’s 2015 solar tender programme.

PEDA Against Relief To Developer

PEDA had argued before the Tribunal that the developer was not entitled to force majeure relief because it had failed to issue formal force majeure notices within the timelines prescribed under the implementation agreement. The agency relied on earlier judgments of APTEL and the Supreme Court to contend that compliance with contractual notice provisions was mandatory for availing force majeure protection.

However, the Tribunal drew a distinction between cases involving external force majeure events unknown to the counterparty and situations where the utility itself had contemporaneous knowledge of the disruption and was actively involved in resolving the issue.

What Led To The Delay?

The principal dispute in the present case related to grid connectivity. Mihit Solar had sought 66 kV connectivity for its projects based on provisions contained in the tender documents issued by PEDA. However, PSPCL later insisted on connectivity at higher voltage levels, leading to delays in project execution. The Tribunal noted that both PEDA and PSPCL were continuously informed about the issue through letters, meetings and joint discussions.

In its order, APTEL observed: “The whole purpose underlying the Article 10.4 notice requirement enabling the counterparty to verify the event and take mitigation steps was entirely fulfilled through the series of communications and the meeting. PEDA was not merely aware; it was actively engaged in resolving the very dispute that constitutes the force majeure event.”

APTEL Clarification

APTEL also clarified that the requirement for force majeure notice is generally intended to ensure that the counterparty is informed about events preventing contractual performance so that mitigation measures can be initiated in time. However, where the utility or nodal agency already possesses complete knowledge of the disruption and has participated in resolution efforts, strict technical insistence on the format or nomenclature of the notice may not be justified.

The Tribunal ultimately upheld PSERC’s decision to condone 72 days of delay linked to the grid connectivity issue and seven days related to the Jat agitation, while disallowing 11 days’ relief granted earlier on account of a local court stay order due to absence of any force majeure notice for that specific event.

APTEL Modifies SCOD Extension

As a result, the Appellate Tribunal for Electricity (APTEL) reduced the total project deadline extension from 90 days to 79 days and revised the commissioning deadline to April 19, 2016. Since the solar projects were already completed before the new deadline, the Tribunal allowed the other reliefs granted to the developer, including the release of bank guarantees.

The ruling could affect future renewable energy disputes related to project delays, especially in cases where utilities or nodal agencies try to deny relief even after being aware of the reasons behind the delay.

whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
global news PEDA PSPCL renewable energy Solar solar projects
Sanjana Negi
  • Website

News contributor at The Battery Magazine. I write on the latest developments in battery technology, energy storage solutions, and power innovations. Committed to delivering accurate and timely updates from the world of batteries.

Keep Reading

NavPrakriti and IIT Kharagpur

NavPrakriti and IIT Kharagpur Partner to Advance Battery Recycling and Critical Mineral Recovery

IIT Guwahati

IIT Guwahati Develops Perovskite Technology Achieving 25.73% Solar Cell Efficiency

India’s Clean Energy Sector

India’s Clean Energy Workforce Grows by 6.6 Lakh, Rooftop Solar Leads Job Creation

Leave A Reply Cancel Reply

sixteen − 4 =

Renewable energy
IIT Guwahati

IIT Guwahati Develops Perovskite Technology Achieving 25.73% Solar Cell Efficiency

June 4, 2026
India’s Clean Energy Sector

India’s Clean Energy Workforce Grows by 6.6 Lakh, Rooftop Solar Leads Job Creation

June 4, 2026
SJVN Flags

SJVN Flags Renewable Power Demand Gap Amid Rising Capacity Additions

June 4, 2026
Kyro Capital

Kyro Capital Launches ₹100 Crore Pre-IPO Fund Targeting Renewable Energy and Growth Sectors

June 3, 2026
Batteries
NavPrakriti and IIT Kharagpur

NavPrakriti and IIT Kharagpur Partner to Advance Battery Recycling and Critical Mineral Recovery

June 4, 2026
Advait Energy Secures 150 MW/300 MWh BESS Project from GUVNL

Advait Energy Secures 150 MW/300 MWh BESS Project from GUVNL

June 4, 2026
cylib and Vianode

cylib and Vianode Partner to Advance Recycled Graphite for EV Batteries

June 4, 2026
Trina Storage

Trina Storage Wins 160 MWh Ultra-High Voltage Battery Project in Japan’s Kyushu Region

June 3, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.