Tata Power Renewable Energy Limited (TPREL) recorded over 130% year-on-year growth in utility-scale project execution during Q2 FY27, commissioning 419 MW of capacity and executing 131.2 MWh of battery energy storage projects. The company had executed 182 MW of utility-scale capacity in the corresponding quarter of FY26.
The performance takes TPREL’s utility-scale execution to 645 MW during the first half of FY27, alongside 161.2 MWh of battery storage projects. Of the storage capacity executed in Q2, 101.2 MWh was for TPREL’s own portfolio, while 30 MWh was delivered for third-party customers.
Key Highlights
- Q2 FY27 execution: 419 MW of utility-scale renewable energy capacity and 131.2 MWh of battery storage projects.
- H1 FY27 execution: 645 MW of utility-scale projects and 161.2 MWh of storage projects.
- Operational portfolio: 7.2 GW of utility-scale renewable energy capacity and 281.2 MWh of battery storage.
- H2 FY27 pipeline: More than 2 GW of projects expected to be executed, alongside 274 MWh of BESS.
- FY28 target: Completion of around 2.6 GW of additional projects, taking overall operational capacity to approximately 12 GW.
Key Projects Commissioned in H1 FY27
During the first half of FY27, TPREL commissioned several projects across wind, solar and energy storage. These include the 100.8 MW Jewali Wind Project, the Kalasar Firm and Dispatchable Renewable Energy (FDRE) project, featuring 227.5 MW of solar capacity and a 101.2 MWh battery energy storage system, the 100 MW Kayathar Group Captive Project, and the 72.5 MW Tata Steel Captive Project.
Following these additions, TPREL’s utility-scale operational portfolio reached 7.2 GW, comprising 5.8 GW of solar, 1.3 GW of wind and 281.2 MWh of battery storage capacity.
Execution Pipeline for FY27 and FY28
Tata Power Renewables expects to execute more than 2 GW of projects during the second half of FY27. The planned additions include 1,075 MW of solar, 969 MW of wind and 274 MWh of BESS. The company also expects to execute an additional 300 MW of third-party projects during the period.
By the end of FY27, TPREL expects its cumulative executed project portfolio to approach 9.3 GW, including 6,899 MW of solar, 2,298 MW of wind and 555.2 MWh of battery storage.
In FY28, the company plans to complete a further 2.6 GW of projects, comprising 1,700 MW of wind, 570 MW of solar and 350 MWh of battery storage. These additions are expected to take its overall operational capacity to approximately 12 GW.
The execution momentum highlights TPREL’s expanding renewable energy portfolio and growing involvement in battery storage projects, as India continues to build capacity for integrating renewable power into its electricity system.