Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Tenders » Andhra Pradesh Floats Tender for 1,250 MW / 5,000 MWh Standalone BESS Projects
Tenders

Andhra Pradesh Floats Tender for 1,250 MW / 5,000 MWh Standalone BESS Projects

Shweta KumariBy Shweta KumariOctober 12, 20264 Mins Read
Facebook Twitter LinkedIn WhatsApp
Andhra Pradesh Floats 1,250 MW / 5,000 MWh BESS Tender

Andhra Pradesh Power Coordination Committee (APPCC) has invited bids to develop 1,250 MW / 5,000 MWh of standalone battery energy storage systems (BESS) across three locations in Andhra Pradesh. The projects will be developed under the Build-Own-Operate (BOO) model through tariff-based competitive bidding, with each project evaluated and awarded separately.

The tender, issued on 7 October 2026, is being conducted on behalf of the state’s three distribution companies: Andhra Pradesh Central Power Distribution Company Limited (APCPDCL), Andhra Pradesh Eastern Power Distribution Company Limited (APEPDCL) and Andhra Pradesh Southern Power Distribution Company Limited (APSPDCL). The systems will be used by the distribution companies on an on-demand basis.

Three Project Locations Identified

The 1,250 MW / 5,000 MWh capacity is divided across three sites:

Project location Capacity Grid connection
Rayalaseema Thermal Power Plant (RTPP), Muddanur 500 MW / 2,000 MWh 400 kV substation
Talaricheruvu Renewable Energy (RE) Project 250 MW / 1,000 MWh 220 kV pooling substation
NP Kunta Renewable Energy Project 500 MW / 2,000 MWh 220 kV substation
Total 1,250 MW / 5,000 MWh

The selected developers will be responsible for developing the battery storage systems and the required power evacuation infrastructure up to the designated grid interconnection points, including associated bays. Each project must be connected at its specified substation.

Contract Period and Commissioning Timeline

The Battery Energy Storage Purchase Agreement (BESPA) will run for 12 years, starting from the Scheduled Commissioning Date or the date of full commissioning, whichever is later.

The scheduled commissioning timeline is 24 months from the effective date of the BESPA for the RTPP and NP Kunta projects. For the Talaricheruvu project, the timeline is 18 months.

The systems must be capable of operating for up to two charge-discharge cycles per day, subject to a maximum of 485 cycles per contract year for each block. The tender specifies a minimum AC-to-AC round-trip efficiency guarantee of 85% and an annual system availability requirement linked to the tender’s performance provisions.

Land and Developer Responsibilities

APPCC and the distribution utilities will identify and allocate land to the selected developers through a Right-of-Use (RoU) arrangement. The land will be provided at an annual charge of ₹1 per acre. The identified land is to be handed over within 60 days of the effective date of the BESPA.

Developers must assess site suitability before bidding and obtain the required approvals and grid connectivity. They will also be responsible for project design, installation, operation, maintenance and safety measures, including fire protection systems. The tender requires fire hydrants, suitable fire barriers and thermal and surveillance cameras in the battery container area.

The tender does not permit merchant capacity: the full contracted project capacity is intended for use by the state distribution companies.

Bid Fees, Guarantees and Key Dates

The tender sets out the following financial and submission requirements:

  • Tender document fee: ₹3 lakh plus 18% GST, non-refundable.
  • Earnest Money Deposit (EMD): ₹5 lakh per MW.
  • Performance Bank Guarantee (PBG): ₹10 lakh per MW, to be submitted before signing the BESPA.
  • Pre-bid meeting: 22 October 2026 at 11:00 AM.
  • Deadline for pre-bid queries: 22 October 2026 at 5:00 PM.
  • Last date for bid submission: 23 November 2026 at 5:00 PM.
  • Technical bid opening: 24 November 2026 at 3:00 PM.

Bidding will follow a single-stage, two-envelope process covering technical and financial bids, followed by an e-reverse auction for each project. Bidders may quote different tariffs for different locations, and the financial evaluation and reverse auction will be conducted separately for each location.

APPCC may also exercise a green-shoe option to procure additional capacity of up to 25% of the specified capacity, subject to the tender’s conditions, including land availability, grid connectivity and regulatory approvals.

The Andhra Pradesh tender provides another opportunity for BESS developers to participate in Andhra Pradesh’s expanding energy storage programme, with the state seeking dispatchable storage capacity to support on-demand electricity requirements.

Last Date 23/11/2026
whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
Andhra Pradesh BESS Tender BOO Model India News Standalone BESS
Shweta Kumari
  • Website
  • LinkedIn

Sub-editor by profession. Love for words and storytelling, where every word narrates a story. Shaping stories in a world powered by electrons—where lithium meets logic, and every spark tells a tale of innovation, sustainability, and our electrified future.

Keep Reading

POWERGRID Commissions Rajasthan 20 GW RE Evacuation

POWERGRID Commissions 20 GW Rajasthan Renewable Energy Evacuation Project

Oswal Pumps Plans 1.2 GW TOPCon Solar Cell Plant by April 2028

Oswal Pumps Plans 1.2 GW TOPCon Solar Cell Plant by April 2028

KP Green Engineering has secured orders worth Rs 272.32 crore

KP Green Engineering Secures ₹272.32 Crore Orders Across Six Business Segments

Leave A Reply Cancel Reply

fourteen − 14 =

Renewable energy
Oswal Pumps Plans 1.2 GW TOPCon Solar Cell Plant by April 2028

Oswal Pumps Plans 1.2 GW TOPCon Solar Cell Plant by April 2028

October 12, 2026
KP Green Engineering has secured orders worth Rs 272.32 crore

KP Green Engineering Secures ₹272.32 Crore Orders Across Six Business Segments

October 12, 2026
Premier Energies Bags Rs 4,001 Crore Q2 Orders

Premier Energies Bags ₹4,001 Crore Q2 Orders as Solar Cell Capacity Reaches 10.6 GW

October 12, 2026
India Turns to 25 GW of Old Wind Farms to Reach 100 GW Goal

India Turns to 25 GW of Old Wind Farms to Reach 100 GW Goal

October 12, 2026
Batteries

CATL Becomes First Battery Company to Join All Three GBA Battery Passport Programme

October 12, 2026
PM Modi Launches 500 MWh BESS

PM Modi Lays Foundation for 500 MWh BESS, ₹17,000 Crore VOC Port Green Hub Planned in Tamil Nadu

October 12, 2026
Trontek Targets 12 GWh Annual BESS Manufacturing Capacity by 2028

Trontek Targets 12 GWh Annual BESS Manufacturing Capacity by 2028

October 12, 2026
Fibocom Showcases IoT Solutions for Smart Energy and EV Battery Tracking at IMC 2026

Fibocom Showcases IoT Solutions for Smart Energy and EV Battery Tracking at IMC 2026

October 9, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.