The Central Electricity Regulatory Commission (CERC) has extended the scheduled commercial operation date (SCOD) of Avaada Inclean Private Limited’s 50 MW solar project in Gujarat to February 24, 2026, allowing the project to retain eligibility for an exemption from Inter-State Transmission System (ISTS) charges.
The order, issued on November 9, 2026, follows delays in the commissioning of transmission infrastructure required to evacuate power from the project. CERC approved the revised SCOD specifically for the purpose of eligibility under ISTS charge waiver provisions.
The solar project is located at Rampar village in Kutch district, Gujarat, and is connected to the 220 kV Lakadiya ISTS pooling substation. The project was developed through Avaada GJ Lakadia Private Limited, a wholly owned subsidiary of Avaada Energy Private Limited.
Avaada had sought regulatory relief after delays in the common transmission system (CTS) infrastructure, including transmission augmentation work at the Lakadiya substation executed by WRSS XXI(A) Transco Limited, affected the project’s commissioning timeline.
The developer stated that its generation facilities and associated transmission readiness were completed within the original schedule. The Central Electricity Authority (CEA) had granted energisation approval on June 30, 2025, which was also the original SCOD. However, the project could not be commissioned due to the unavailability of the required transmission infrastructure.
The delays also affected power procurement arrangements, with the prospective buyer, Vretanta Clean India Private Limited, deferring the signing of a binding power purchase agreement in April 2025 amid uncertainty over the transmission system’s completion. The parties subsequently entered into a conditional, non-binding memorandum of understanding.
A committee constituted under the applicable sharing regulations examined Avaada’s representation and submitted reports in November 2025 and March 2026. It concluded that the commissioning delay was not attributable to the developer and recommended two six-month extensions of the SCOD, up to June 30, 2026, or until the commissioning of the common transmission infrastructure, whichever occurred earlier. The committee also recommended allowing up to 60 days for commissioning preparations after the transmission system became operational, subject to the prescribed limits.
According to records submitted by the Central Transmission Utility of India Limited, WRSS XXI(A) Transco Limited declared commercial operation of the Lakadiya transformation augmentation and associated 220 kV line bay on February 10, 2026. Project connectivity subsequently became effective on March 28, 2026.
Avaada’s project completed its trial run on February 19, 2026, and achieved commercial operation of the full 50 MW capacity on February 24, 2026.
After reviewing the regulatory provisions and supporting documents, CERC determined that the project met the conditions for extending ISTS charge waiver eligibility. The commission considered the original commissioning schedule, transmission infrastructure delays and the project’s eventual commissioning.
The SCOD extension has been approved specifically for ISTS charge waiver eligibility and does not alter the order’s limited regulatory purpose.





