Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Renewable energy » Solar » CERC Extends SCOD of Avaada’s 50 MW Gujarat Solar Project to February 24, 2026
Solar

CERC Extends SCOD of Avaada’s 50 MW Gujarat Solar Project to February 24, 2026

Shivangi GuptaBy Shivangi GuptaNovember 21, 20263 Mins Read
Facebook Twitter LinkedIn WhatsApp
CERC Extends SCOD of Avaada’s 50 MW Gujarat Solar Project to February 24, 2026

The Central Electricity Regulatory Commission (CERC) has extended the scheduled commercial operation date (SCOD) of Avaada Inclean Private Limited’s 50 MW solar project in Gujarat to February 24, 2026, allowing the project to retain eligibility for an exemption from Inter-State Transmission System (ISTS) charges.

The order, issued on November 9, 2026, follows delays in the commissioning of transmission infrastructure required to evacuate power from the project. CERC approved the revised SCOD specifically for the purpose of eligibility under ISTS charge waiver provisions.

The solar project is located at Rampar village in Kutch district, Gujarat, and is connected to the 220 kV Lakadiya ISTS pooling substation. The project was developed through Avaada GJ Lakadia Private Limited, a wholly owned subsidiary of Avaada Energy Private Limited.

Avaada had sought regulatory relief after delays in the common transmission system (CTS) infrastructure, including transmission augmentation work at the Lakadiya substation executed by WRSS XXI(A) Transco Limited, affected the project’s commissioning timeline.

The developer stated that its generation facilities and associated transmission readiness were completed within the original schedule. The Central Electricity Authority (CEA) had granted energisation approval on June 30, 2025, which was also the original SCOD. However, the project could not be commissioned due to the unavailability of the required transmission infrastructure.

The delays also affected power procurement arrangements, with the prospective buyer, Vretanta Clean India Private Limited, deferring the signing of a binding power purchase agreement in April 2025 amid uncertainty over the transmission system’s completion. The parties subsequently entered into a conditional, non-binding memorandum of understanding.

A committee constituted under the applicable sharing regulations examined Avaada’s representation and submitted reports in November 2025 and March 2026. It concluded that the commissioning delay was not attributable to the developer and recommended two six-month extensions of the SCOD, up to June 30, 2026, or until the commissioning of the common transmission infrastructure, whichever occurred earlier. The committee also recommended allowing up to 60 days for commissioning preparations after the transmission system became operational, subject to the prescribed limits.

According to records submitted by the Central Transmission Utility of India Limited, WRSS XXI(A) Transco Limited declared commercial operation of the Lakadiya transformation augmentation and associated 220 kV line bay on February 10, 2026. Project connectivity subsequently became effective on March 28, 2026.

Avaada’s project completed its trial run on February 19, 2026, and achieved commercial operation of the full 50 MW capacity on February 24, 2026.

After reviewing the regulatory provisions and supporting documents, CERC determined that the project met the conditions for extending ISTS charge waiver eligibility. The commission considered the original commissioning schedule, transmission infrastructure delays and the project’s eventual commissioning.

The SCOD extension has been approved specifically for ISTS charge waiver eligibility and does not alter the order’s limited regulatory purpose.

whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
Avaada Energy CERC Gujarat Solar Project India News ISTS Charges Solar Power
Shivangi Gupta
  • Website

Shivangi Gupta is a journalist passionate about writing and delivering accurate, clear, and informative news stories across a wide range of topics.

Keep Reading

Genus Innovation

Genus Innovation: From Power Backup to Intelligent Solar and Storage

Servotech Renewable

Servotech Renewable: From Residential Lithium Batteries to Megawatt-Scale BESS

India’s Battery Storage Boom Faces Its Biggest Test: Project Execution

India’s Battery Storage Boom Faces Its Biggest Test: Project Execution

Leave A Reply Cancel Reply

five − 4 =

Renewable energy
GERC Approves 500 MW Wind Power Procurement for GUVNL at Tariffs of ₹3.51–₹3.515/kWh

GERC Approves 500 MW Wind Power Procurement for GUVNL at Tariffs of ₹3.51–₹3.515/kWh

November 21, 2026
CERC Extends SCOD of Avaada’s 50 MW Gujarat Solar Project to February 24, 2026

CERC Extends SCOD of Avaada’s 50 MW Gujarat Solar Project to February 24, 2026

November 21, 2026
Hoymiles Showcases Residential Solar, Storage and Microinverter Solutions at RE+ 2026

Hoymiles Showcases Residential Solar, Storage and Microinverter Solutions at RE+ 2026

November 21, 2026
Rajasthan Accelerates Battery and Pumped Storage Projects to Target Energy Surplus

Rajasthan Accelerates Battery and Pumped Storage Projects to Target Energy Surplus

November 21, 2026
Batteries
HiTHIUM Unveils Integrated C&I Microgrid Solution Featuring 1,022 kWh Energy Storage System

HiTHIUM Unveils Integrated C&I Microgrid Solution Featuring 1,022 kWh Energy Storage System

November 21, 2026
MULTIFIT Strengthens Its Solar and Battery Storage Portfolio

MULTIFIT Expands Solar Storage Portfolio with Hybrid Inverters and Integrated Battery Systems

November 20, 2026
Four Firms Advance Under Rare Earth Magnet Scheme

Coal India, ReNew Among Four Firms Advancing Under ₹7,280-Crore Rare Earth Magnet Scheme

November 20, 2026
Juniper Green Commissions 108.50 MWp Solar, 94.77 MWh BESS

Juniper Green Adds 108.50 MWp Solar and 94.77 MWh Storage to Portfolio

November 20, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.