The Gujarat Electricity Regulatory Commission (GERC) has approved the procurement of 500 MW of wind power by Gujarat Urja Vikas Nigam Limited (GUVNL) at tariffs ranging from ₹3.51 to ₹3.515 per unit, paving the way for 25-year Power Purchase Agreements (PPAs) with three renewable energy developers.
The approval, issued on November 19, 2026, allows GUVNL to proceed with the procurement following a competitive bidding process conducted to meet the Renewable Purchase Obligations (RPOs) of Gujarat’s four state-owned distribution companies — DGVCL, MGVCL, PGVCL and UGVCL.
GUVNL launched the tender on April 30, 2026, for 250 MW of grid-connected wind power projects located anywhere in India, with an additional 250 MW offered under a greenshoe option. The procurement is also expected to support grid balancing during non-solar hours and complement Gujarat’s daytime solar generation, particularly amid electricity demand from agricultural consumers under the Kisan Suryoday Yojana.
NLC India Renewables Secures 300 MW
The tender received bids from seven companies offering a combined 485 MW. All seven initially qualified for financial bidding following the techno-commercial evaluation, but NANJ Solar Private Limited was subsequently eliminated as the highest bidder under the tender provisions.
The remaining six bidders participated in the electronic reverse auction held on July 9, 2026, where tariffs for the initial 250 MW capacity ranged between ₹3.51 and ₹3.52 per unit.
The initial allocation was as follows:
| Developer | Capacity | Tariff |
|---|---|---|
| NLC India Renewables | 100 MW | ₹3.51/kWh |
| Powerica Ltd. | 50 MW | ₹3.51/kWh |
| Juniper Green Energy | 50 MW | ₹3.51/kWh |
| CU-Built Renewable Energy | 50 MW | ₹3.52/kWh |
| Total | 250 MW | — |
Following the auction, GUVNL exercised the greenshoe option to procure an additional 250 MW. Powerica and Juniper Green Energy declined their additional allocations, while CU-Built Renewable Energy accepted another 50 MW. NLC India Renewables took the remaining 200 MW.
As a result, NLC India Renewables’ allocation increased to 300 MW at ₹3.51 per unit, while CU-Built Renewable Energy secured a total of 100 MW at a weighted tariff of ₹3.515 per unit.
GERC Finds Tariffs Competitive With Recent Wind Auctions
During the regulatory hearing on November 17, 2026, the participating developers raised no objections to the procurement process or the discovered tariffs.
GERC observed that the approved rates were competitive compared with recent wind power auctions conducted by central procurement agencies such as Solar Energy Corporation of India (SECI) and SJVN, where tariffs ranged from ₹3.64 to ₹4.17 per unit.
The commission directed GUVNL to execute the PPAs within 15 business days, include applicable late payment surcharge provisions and publish the successful bidders and approved tariffs on its website for 30 days to ensure transparency.
The approved procurement will add 500 MW of wind power to GUVNL’s planned renewable energy portfolio, helping Gujarat diversify its renewable supply and improve electricity availability beyond solar generation hours.