Close Menu
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
Facebook LinkedIn WhatsApp
The Battery MagazineThe Battery Magazine
  • Just In
  • Batteries
    • Battery Manufacturing (BESS)
    • Battery Materials & Chemistries
    • Battery Recycling
    • C&I Storage
  • Solar
  • Renewable energy
    • Wind Energy
    • Hydropower
    • Green Hydrogen
    • Bioenergy
  • Tenders
    • Energy Storage
    • Solar Energy
    • Wind Energy
  • Policy
    • Storage
    • Solar
    • Wind
    • EV
    • Transmission
  • EV
    • EV Batteries
    • EV Charging Infrastructure
    • Electric Mobility Trends
  • Grid
    • Transmission & Distribution
    • Grid Infrastructure
    • Power Generation
    • Power Equipments
  • Exclusive
    • Cover Story
    • Watt Matters
    • Perspective
    • Articles
  • More
    • E-Mag
    • Events
    • Contact Us
LinkedIn Facebook WhatsApp YouTube
The Battery MagazineThe Battery Magazine
Home » Tenders » POWERGRID Invites Bids for 187.5 MW/750 MWh BESS Project at Telangana Substation
Tenders

POWERGRID Invites Bids for 187.5 MW/750 MWh BESS Project at Telangana Substation

Shweta KumariBy Shweta KumariOctober 13, 20262 Mins Read
Facebook Twitter LinkedIn WhatsApp
POWERGRID floats 187.5 MW/750 MWh Telangana BESS Tender

Power Grid Corporation of India Limited (POWERGRID) has invited bids for the development of a 187.5 MW/750 MWh battery energy storage system (BESS) in Telangana under Package TS-BESS-01. The four-hour storage project is associated with the Maheswaram 400/220 kV substation operated by Telangana’s transmission utility, TGTRANSCO. The tender was published on 12 October 2026 under the tariff-based competitive bidding framework.

The project covers the design, supply, erection, testing and commissioning of the BESS, along with operation and maintenance. The facility is expected to be completed within 15 months from the employer handing over the site. The selected contractor will also be responsible for comprehensive maintenance for 15 years after commissioning.

Particular Details
Tendering authority POWERGRID
Package TS-BESS-01
Project location Maheswaram 400/220 kV substation, Telangana
BESS capacity 187.5 MW/750 MWh
Storage duration 4 hours
Tender reference CC/T/W-BESS/DOM/A02/26/14098
RFX number 5002005732
Tender publication date 12 October 2026
Document submission deadline 17 October 2026, 11:55 PM
Bid submission deadline 19 October 2026, 11:00 AM
Bid opening 19 October 2026, 11:30 AM
Tender document fee ₹25,000
EMD Listed as zero on the POWERGRID portal; bidders should confirm the applicable conditions in the tender documents

EMD Listed as zero on the POWERGRID portal; bidders should confirm the applicable conditions in the tender documents. The tender documents are available through POWERGRID’s official tender portal.

Bidding Framework and Implementation

The project is being pursued through tariff-based competitive bidding with viability gap funding support through the Power System Development Fund (PSDF). Telangana Power Generation Corporation Limited (TGGENCO) is identified in the available reporting as the bid process coordinator responsible for the Request for Selection (RfS).

POWERGRID intends to pre-select a qualified bidder with the required technical capability and the lowest evaluated bid to partner in the tariff-bidding process. A memorandum of understanding is expected to be signed with the selected bidder before POWERGRID submits its tariff bid. The contract for project execution would follow if POWERGRID succeeds in the wider bidding process. Therefore, this tender should not be described as a direct award of the BESS project to a developer at this stage.

The storage installation is intended to support grid flexibility as renewable energy generation increases. Battery storage can absorb electricity when supply is available and discharge it during periods of higher demand or lower renewable generation.

Capacity 187.5 MW/750 MWh BESS
Location Maheswaram 400/220 kV substation, Telangana
Last Date 19/10/2026
whatsapp icon Electrify your feed! Click here to join our Whatsapp group and to get the latest updates, expert insights, and innovations driving India’s energy storage revolution.
BESS tender India News Power System Development Fund POWERGRID Powergrid BESS Project TGTRANSCO
Shweta Kumari
  • Website
  • LinkedIn

Sub-editor by profession. Love for words and storytelling, where every word narrates a story. Shaping stories in a world powered by electrons—where lithium meets logic, and every spark tells a tale of innovation, sustainability, and our electrified future.

Keep Reading

Tata Power, Imperial College Join Hands for Energy Storage

Tata Power, Imperial College London Join Hands to Advance Energy Storage and Smart Grid Technologies

WBSEDCL Floats Tender for 50 MW Solar Project

WBSEDCL Floats Tender for 50 MW Solar Project with 40 MWh Battery Storage

MeECL and TERI Sign MoU to Advance Renewable Energy and Storage in Meghalaya

MeECL and TERI Sign MoU to Advance Renewable Energy and Storage in Meghalaya

Leave A Reply Cancel Reply

nineteen + 4 =

Renewable energy
Tata Power, Imperial College Join Hands for Energy Storage

Tata Power, Imperial College London Join Hands to Advance Energy Storage and Smart Grid Technologies

October 13, 2026
MeECL and TERI Sign MoU to Advance Renewable Energy and Storage in Meghalaya

MeECL and TERI Sign MoU to Advance Renewable Energy and Storage in Meghalaya

October 13, 2026
Sunsure Energy Signs 30 MWp Solar PPA with Evonith Steel

Sunsure Energy Signs 30 MWp Solar PPA with Evonith Steel to Cut Industrial Emissions

October 13, 2026
GREW Solar Invites Industry to #BrewWithGrew at REI Expo

GREW Solar Invites Industry to #BrewWithGrew at REI Expo and BRE Summit 2026

October 13, 2026
Batteries
NEU Battery Materials Raises US 7.6 Million Dollar

NEU Battery Materials Raises US$7.6 Million to Scale LFP Battery Recycling

October 13, 2026
Trinasolar Unveils 760W TOPCon Solar Modules

Trinasolar Introduces 760W TOPCon Solar Modules and 6.25 MWh BESS in Vietnam

October 13, 2026
Tata Power Renewable Energy Limited

Tata Power Renewables Records Over 130% YoY Growth, Executes 419 MW in Q2 FY27

October 13, 2026

CATL Becomes First Battery Company to Join All Three GBA Battery Passport Programme

October 12, 2026

Subscribe for Updates

Get the latest news about energy storage in your inbox.

    © 2026 Thebatterymagazine.com.
    • Home
    • About Us
    • Contact Us
    • Privacy Policy
    • Terms of Service

    Type above and press Enter to search. Press Esc to cancel.